Welding Inspection Checklist: Before, During, and After Welding

Welding Inspection Checklist — Before, During & After | WeldFabWorld
Inspection & Testing By WeldFabWorld Published: August 11, 2025 Updated: September 4, 2025

Welding Inspection Checklist: Before, During, and After Welding

A welding inspection checklist is the backbone of any quality-controlled fabrication programme. Whether you are a Certified Welding Inspector (CWI), a QC engineer on a pressure vessel shop floor, or a site supervisor overseeing structural steel erection, a systematic checklist ensures that nothing critical is missed — from verifying the right WPS is at the workstation before the first arc is struck, to confirming that post-weld NDT results meet code acceptance criteria before a joint is closed up. The cost of catching a defect at the right inspection stage is a fraction of the cost of finding it during hydrostatic testing, commissioning, or worse, in service.

Welding inspection is conducted in three distinct phases: before welding (pre-weld), during welding (in-process), and after welding (post-weld). Each phase has its own set of checks, documentation requirements, and acceptance criteria. Codes such as ASME Section VIII Div. 1, ASME B31.3, AWS D1.1, and ISO 3834 all mandate inspection activities at defined stages, and the Inspection and Test Plan (ITP) is the document that translates those code requirements into a project-specific, auditable inspection programme.

This guide provides a comprehensive, technically detailed checklist for all three inspection phases — covering documentation, material verification, fit-up, in-process parameter monitoring, NDT selection, PWHT verification, and records management. It is written to match the rigour expected of a working CWI or welding engineer operating under ASME, AWS, or ISO inspection regimes.

Welding inspector performing visual inspection on a weld joint with measuring gauge, checklist visible in background
Figure 1 — Welding inspection in practice: visual examination with a weld gauge is the foundation of every phase of inspection, supplemented by dimensional measurement, parameter monitoring, and NDT as required by the applicable code and ITP.
3
Inspection Phases
Pre-weld, in-process, and post-weld — each with mandatory hold points.
14
Pre-Weld Checks
Documentation through preheat — all must be confirmed before the first arc strike.
7
In-Process Checks
Parameter monitoring, interpass control, and in-process NDT during welding.
6
Post-Weld Checks
Visual, dimensional, NDT, PWHT, and final documentation before acceptance.
Welding Inspection — Three-Phase Timeline 1 PRE-WELD Documentation review WPS / WPQ verification Material identification Joint fit-up & cleanliness Preheat verification Equipment check ITP / hold points set 2 IN-PROCESS Welding parameters Interpass temperature Interpass cleaning Pass sequence Backgouging inspection In-process NDT Weld pass visual check 3 POST-WELD Visual inspection (VT) Weld profile & dimensions Dimensional accuracy NDT (RT, UT, MT, PT) PWHT (if required) Hardness testing Inspection reports
Figure 2 — The three-phase welding inspection timeline. Each phase has mandatory checks and defined hold points. Missing any phase — particularly pre-weld documentation — invalidates the inspection record and may require rework or re-inspection.
1 Phase 1 — Pre-Weld Inspection Checklist (Before Welding)

Pre-weld inspection is where defect prevention happens. Every non-conformance caught before the first arc is struck eliminates the far greater cost — in time, material, and project schedule — of rework after welding. This phase is the most document-intensive and sets the conditions for all subsequent inspection activities.

1. Review All Applicable Documentation

1
Verify WPS availability and applicability

Confirm the approved Welding Procedure Specification is posted at or near the work station. Check that it covers the specific base material P-Number combination, filler F-Number, joint type, welding position, and thickness range for the joint being welded. A WPS that covers P1 groove welds in position 1G does not cover the same joint in position 6G. Check the WPS revision number against the project’s document register — only the current approved revision is valid.

2
Verify construction drawings are current revision

Confirm that the isometric or fabrication drawing at the work front is the latest approved revision. Superseded drawings must be physically removed from the work area and marked void. Welding to an outdated drawing is a common cause of dimensional non-conformance and weld map traceability failures.

3
Confirm Inspection and Test Plan (ITP) is active

The ITP must be in place and understood by all inspection parties before fabrication commences. All hold points (H) and witness points (W) must be marked on the weld map or traveller. Third-party inspection agencies and client representatives must have received formal notification of the ITP in advance of any hold point being reached.

2. Verify Welder Qualification

4
Check Welder Performance Qualification (WPQ) certificates

Every welder must hold a current, valid WPQ certificate covering the process, material, position, and thickness range of the joint they are about to weld. Under ASME Section IX QW-322, welder performance qualifications expire after six months if the welder has not been engaged in the welding process they are qualified for. Verify the most recent production weld date against the WPQ expiry. A welder with an expired WPQ must not weld until requalification is completed.

5
Confirm welder identification system is in place

Each welder must have a unique stamp or identification mark, and all production welds must be marked with the welder’s ID on the weld map, traveller, or directly on the joint (where permitted). This traceability is essential for responding to NDT non-conformances — if RT reveals a rejectable defect, the weld map identifies the welder and the WPS used, enabling root cause investigation.

3. Establish Recordkeeping and Rejection Systems

6
Establish weld traveller and inspection log

A weld traveller accompanies each weld joint from fit-up through final NDT acceptance. It records the WPS number, welder ID, fit-up acceptance, preheat measurement, welding parameters, NDT results, and final disposition. Every inspection sign-off must be by name, certification, date, and time. Blank fields on a traveller are a non-conformance during audit.

7
Set up non-conformance identification and tagging system

Any component or joint that fails an inspection stage must be immediately identified with a rejection tag and physically segregated from accepted work. Yellow tags (hold) and red tags (reject) are the standard convention in most QA systems. Rejected items must not be moved to the next work stage until the non-conformance has been formally dispositioned — repair, rework, or use-as-is with engineering concurrence.

4. Inspect Welding Equipment and Consumables

8
Inspect and record welding equipment condition and calibration

Verify that the welding power source amperage and voltage meters are calibrated and within their calibration validity period. Check cables, earth clamps, gas hoses, and torch/gun condition for damage or wear. A poor earth connection causes arc instability that directly affects weld quality. Record the equipment serial number on the weld traveller — if a defect is later found in a production weld, the equipment used can be traced and tested.

9
Verify base material identification and MTR traceability

Check the heat number on the base material against the material test report (MTR/CMTR). The MTR must confirm that chemical composition, mechanical properties, and heat treatment comply with the applicable material specification. For pressure equipment under ASME, all pressure-boundary material must carry ASME-required markings and be traceable to an MTR. Verify that the P-Number on the MTR matches the P-Number stated in the WPS.

10
Verify filler metal classification, certification, and storage

Confirm that the filler metal classification (e.g., E7018-H4R, ER308L) matches the WPS requirement. Check the filler metal manufacturer’s certification for compliance with the applicable SFA specification. Low-hydrogen SMAW electrodes (E7016, E7018) must be stored in a heated oven at 120–150°C after opening — inspect the oven temperature log. Filler wires must be free from surface corrosion, and GTAW wires must be clean and dry. Contaminated or improperly stored consumables are a leading cause of hydrogen cracking and porosity. For more on consumable classification systems, see our dedicated guide.

5. Inspect Joint Preparation and Fit-Up

11
Verify weld preparation geometry

Inspect the bevel angle, root face, and root gap against the WPS and drawing requirements using a weld gauge or protractor. Common WPS requirements for single-V groove welds: included angle 60–70°, root face 1–1.5 mm, root gap 2–3 mm. Deviations from the qualified range are changes to a non-essential variable (generally) but may affect fusion quality if outside practical limits. Record actual measured dimensions on the traveller. See our guide on welding joint types and geometry for reference values by joint configuration.

12
Verify alignment, hi-lo, and root gap

Measure and record joint alignment (offset/hi-lo) across the joint interface. ASME B31.3 Process Piping limits hi-lo (axial misalignment) to 1.5 mm or 1/4 of the nominal wall thickness, whichever is less. AWS D1.1 permits a maximum root pass hi-lo of 3 mm before correction. Excessive hi-lo concentrates stress at the inside weld toe and is a fatigue crack initiation site in cyclic service. Confirm the root gap is within the WPS range and consistent around the circumference for pipe joints.

13
Verify joint cleanliness

Inspect the joint faces and adjacent base metal surfaces (typically 25 mm back from the weld toe) for oil, grease, paint, mill scale, rust, moisture, and other contaminants. Any contamination within the weld zone is a source of porosity, hydrogen cracking, or inclusions. Clean using a dedicated stainless wire brush (for stainless and nickel alloys), appropriate degreasing solvent, or grinding — never use tools shared with carbon steel on stainless steel joints. For austenitic stainless, any iron contamination risks pitting corrosion in service.

14
Verify preheat temperature and method

Confirm that the preheat temperature required by the WPS has been achieved and is uniform across the joint before the root pass commences. Measure with a calibrated contact thermometer or Tempilstik at a point approximately 75 mm from the weld centreline for wall thicknesses above 50 mm, or 38 mm for thinner material (per AWS D1.1). Colour estimation of preheat temperature is not acceptable. For carbon and low-alloy steels, preheat prevents hydrogen-induced cracking (HICC) by keeping the HAZ above the martensite start temperature during cooling. Use our carbon equivalent calculator to determine minimum preheat requirements from base material chemistry.

Code Reference: All 14 pre-weld checks above align with the requirements of ASME Section VIII Div. 1 (UW-26 to UW-31), ASME B31.3 (para. 328.4), AWS D1.1 (Clause 6.4), and ISO 3834-2 (Clause 8). The ITP must map each check to the specific code clause that mandates it, enabling traceability during third-party audit.
2 Phase 2 — In-Process Inspection Checklist (During Welding)

In-process inspection monitors the welding operation in real time to ensure that the welder stays within the WPS parameter envelope and that each weld pass is acceptable before the next one is deposited. Defects caught during welding are far cheaper to repair than those found by post-weld NDT — grinding out a single bad pass costs minutes; excavating and rewelding a completed joint costs hours and may require re-qualification of the repair procedure.

1. Monitor Welding Parameters Against WPS

1
Monitor and record amperage, voltage, and travel speed per pass

Confirm that the welding current, arc voltage, and travel speed measured during each pass fall within the ranges specified in the WPS. Use a calibrated clamp-on ammeter and voltmeter — do not rely on the machine’s built-in display, which may have been knocked out of calibration. Travel speed should be timed over a measured bead length (e.g., time in seconds to travel 100 mm). From these three parameters, calculate heat input per pass: H = (V × I × 60) / (TS × 1000) kJ/mm. For heat-sensitive materials such as P91 chrome-moly and duplex stainless steel, heat input is a controlled essential variable and must be recorded for every pass.

2
Confirm shielding gas type, purity, and flow rate

For GTAW and GMAW processes, verify the shielding gas cylinder label matches the WPS-specified composition (e.g., 100% Ar for TIG, Ar/CO₂ blend for MIG). Check the flow meter setting against the WPS range. Wind shields must be in place for outdoor or draughty work areas — excessive wind disperses the shielding envelope and causes porosity. For back-purge on stainless steel piping, monitor residual oxygen content at the purge outlet with a calibrated O₂ analyser; back purge must read below 0.10% O₂ before and throughout root welding.

2. Inspect Each Weld Pass

3
Visually inspect each pass before the next is deposited

After completing each weld pass and before starting the next, the inspector (or welder acting as inspector) must examine the pass surface for: cracks (always an immediate stop-work condition), porosity, arc strikes outside the groove, slag entrapment along the fusion line, incomplete fill at the toes, and cold lap. Any rejectable condition must be removed by grinding or gouging and verified clean before the next pass is allowed. This inter-pass visual check is mandated by AWS D1.1 Clause 6.25 and ASME Section IX QW-194.

4
Verify interpass cleaning between every pass

All slag, flux residue, and surface oxides must be removed between passes using a chipping hammer followed by a wire brush. Particular attention must be paid to the toes of the previous bead, where slag trapping is most common. For SAW and SMAW, slag removal is critical — any remaining slag becomes a planar inclusion in the next pass, which RT will detect as a linear indication. Check that only approved tools are being used — wire brushes for stainless must never be shared with carbon steel to prevent iron contamination and subsequent pitting corrosion.

5
Measure and record interpass temperature before every pass

Measure interpass temperature at the weld toe before every subsequent pass commences. The measurement point must be within 25–75 mm of the joint, depending on the applicable specification. Record actual readings on the weld traveller alongside the pass number. If the maximum interpass temperature specified in the WPS is exceeded, welding must stop and the joint allowed to cool. On P91 and P92 chrome-moly steels, excessive interpass temperature causes grain coarsening in the HAZ and promotes Type IV creep cracking sites. On duplex stainless steels, it drives sigma phase precipitation. Neither failure mode is detectable by standard production NDT — they are revealed only in service or by metallurgical sectioning during root cause investigation.

6
Verify weld pass sequence and number of passes

Confirm that the welder is following the pass sequence specified in the WPS or associated weld procedure detail. For multi-pass welds, the sequence affects residual stress distribution, HAZ tempering, and distortion. A balanced welding sequence on double-sided groove welds (alternating sides) minimises angular distortion. For piping welds in fixed positions, the recommended practice is to divide the weld into four clock-face quadrants and balance the fill sequence to minimise ovality and end-of-weld distortion.

7
Inspect backgouged surfaces before second-side welding

Where the WPS specifies backgouging from the second side (common on double-sided groove welds and fillet repair welds), inspect the gouged surface before welding resumes. The backgouged groove must be: free from remaining weld metal not yet fused into the root (verified visually and by MT or PT if specified); smooth and free from sharp notches that would cause localised stress concentration; and ground clean of carbon contamination if carbon arc gouging was used (mandatory for stainless steel and chrome-moly alloys). For in-process NDT requirements (MT or UT on intermediate passes for thick-section welds), follow the specific requirements of the applicable code or project specification.

Warning — Arc Strikes: Arc strikes outside the defined weld zone are always a non-conformance and must be addressed immediately. The localized rapid heating and quenching of an arc strike produces a brittle martensitic spot in the base metal that is a potential fracture initiation site. The procedure for arc strike remediation is: grind the arc strike flush, perform MT or PT examination to confirm no cracking, measure the remaining wall thickness, and document the repair on a non-conformance report. Never attempt to weld over or melt out an arc strike without engineering concurrence.
3 Phase 3 — Post-Weld Inspection Checklist (After Welding)

Post-weld inspection provides the final confirmation that the completed weld joint meets all applicable code and project requirements. It begins with visual examination — which is always the first and mandatory inspection method — and progresses through dimensional verification, NDT, and PWHT monitoring as required. No joint may be accepted or released for pressure testing, painting, or final assembly without full post-weld inspection sign-off.

1. Visual Inspection of the Finished Weld

1
Perform visual inspection per applicable code acceptance criteria

Visual examination (VT) of the completed weld is mandatory under all construction codes and is the prerequisite for any other inspection method. VT must be performed in accordance with AWS QC1 or the applicable code by a qualified inspector with adequate lighting (minimum 500 lux at the weld surface per ISO 17637). Inspect the weld cap and both weld toes for: cracks, crater cracks, and HAZ cracking; undercut depth (measured with a weld undercut gauge — maximum 0.25 mm for cyclic service per AWS D1.1, 0.8 mm for static per D1.1 Table 9.1); overlap or cold lap at toes; surface porosity; excessive or insufficient reinforcement; and weld spatter within the inspection zone. Every visual observation must be recorded on the inspection form — not just rejectable conditions.

2
Measure weld size, length, and profile with calibrated weld gauge

For fillet welds: measure throat thickness (minimum specified on drawing) and leg length at multiple locations around the joint. AWS D1.1 requires that leg length shortfall exceeding 2 mm in any 50 mm of weld length be repaired. For groove welds: measure reinforcement height (cap height above flush) — maximum 3 mm for most structural codes. Verify that the weld length on fillet welds matches the drawing specification. Use a calibrated weld gauge (Bridge Cam, Hi-Lo gauge, or equivalent) — engineer’s scale estimation is not acceptable for code inspection. Record all measurements with the gauge type and calibration reference number.

2. Dimensional and Geometric Verification

3
Verify overall weldment dimensional accuracy

Measure the completed weldment against the dimensional tolerances on the fabrication drawing for: overall length; squareness and angularity; straightness (bow or sweep) of the assembly; flatness of flat surfaces; flange face perpendicularity and bolt-hole orientation on piping spools; and nozzle projection and orientation on pressure vessels. For piping spools, dimensional tolerances are typically governed by the construction standard (e.g., ASME B31.3 or the piping specification) and the client’s spool dimensional control procedure. Out-of-tolerance conditions may require cutting and re-welding rather than mechanical force correction, which can introduce residual stress.

3. Non-Destructive Testing

4
Perform and document all required NDT to applicable procedures

Conduct all NDT methods specified in the ITP, project specification, and construction code. Every NDT examination must be performed by a certified examiner (minimum Level II per SNT-TC-1A or ISO 9712), using a calibrated, written, and approved examination procedure. NDT results must be documented on a formal report that includes: examiner name, certification level, and expiry date; procedure number and revision; equipment identification and calibration status; examination coverage (percentage or area); and the accept/reject disposition with reference to the applicable acceptance standard. The NDT report must be signed by the Level II or III examiner and reviewed by the responsible inspector. For a comprehensive overview of all NDT methods used in welding, see our guide on non-destructive testing methods.

4. Post-Weld Heat Treatment Monitoring

5
Verify PWHT time-temperature record and thermocouple coverage

If PWHT is required by the WPS or construction code, verify: the number and location of thermocouples meet the applicable code requirement (ASME Section VIII Div. 1 UCS-56 typically requires at least one thermocouple per 10 metres of heated length or part thereof, plus one at each end of the soak band); the actual soak temperature is within the code-specified range (e.g., 595–720°C for P1 carbon steel under ASME, depending on thickness); the hold time at temperature meets the code minimum; and the heating and cooling rates are within the specified limits (typically 55–220°C/hour maximum for carbon steel depending on thickness). The original chart recorder strip or data logger output is a permanent quality record — it cannot be rerun or reproduced if lost. Hardness testing after PWHT is required for sour service and certain alloy steel weldments to verify the PWHT achieved the target reduction in HAZ hardness.

5. Compile and Issue Final Inspection Reports

6
Compile complete weld documentation package and issue release

The completed weld documentation package for each joint or weld line must include: the completed weld traveller with all inspection sign-offs; the approved WPS referenced; welder ID and WPQ certificate reference; material traceability (MTR/CMTR references for base and filler materials); pre-weld inspection report; in-process parameter records; all NDT reports with examiner certifications; PWHT chart and thermocouple calibration records (where applicable); any NCR reports and their disposition records; and the dimensional inspection record. The inspector must sign the final acceptance statement on the traveller. Only after complete documentation sign-off may the joint proceed to pressure testing, painting, or final assembly. No documentation gaps are acceptable — every blank field on a weld traveller that was not completed at the time of inspection is a non-conformance.

NDT Method Selection — Defect Type vs. Technique

Selecting the correct NDT method requires understanding both the type of defect anticipated and the physical constraints of the weld joint. The following table summarises the applicability and limitations of the principal NDT methods used in welding inspection.

NDT Method Defect Type Detected Applicability Limitation Code Reference
Visual Testing (VT) Surface only All materials; mandatory for every weld Open to surface defects only; lighting and access critical AWS QC1; ISO 17637; ASME V Art. 9
Radiographic Testing (RT) Volumetric Butt welds; pipe and plate; all materials Less sensitive to planar defects parallel to beam; radiation hazard; film archiving ASME V Art. 2; AWS D1.1 Annex I; ISO 17636
Ultrasonic Testing (UT / PAUT) Volumetric + planar All materials; thick sections; preferred for planar cracks Operator skill-dependent; rough surfaces reduce coupling ASME V Art. 4; AWS D1.1 Annex K; ISO 17640
Magnetic Particle Testing (MT) Surface + near-surface Ferromagnetic materials (carbon steel, low-alloy) only Not applicable to austenitic SS, aluminium, or non-magnetic alloys ASME V Art. 7; AWS D1.1 Annex C; ISO 17638
Liquid Penetrant Testing (PT) Surface open only All materials including non-magnetic (SS, aluminium, titanium) Open-to-surface defects only; rough weld surfaces require dressing first ASME V Art. 6; AWS D1.1 Annex D; ISO 3452
Eddy Current Testing (ET) Surface + near-surface Conductive materials; tube inspection; surface crack detection Not effective for deep subsurface defects; complex geometry limitation ASME V Art. 8; ISO 15548
Time of Flight Diffraction (TOFD) Volumetric + planar Pressure vessels; thick-section butt welds; high sensitivity Dead zones near surface; complex analysis; operator qualification ASME V Art. 4 App. N; ISO 10863

Visual Inspection Acceptance Criteria — Key Parameters

The following table consolidates key visual acceptance criteria from AWS D1.1 (structural steel) and ASME Section VIII Div. 1 (pressure vessels) for quick reference. Always confirm against the specific code edition and applicable project specification — these values represent the minimum code requirement and project specifications may be more restrictive.

Discontinuity AWS D1.1 (Static) AWS D1.1 (Cyclic) ASME Section VIII Disposition
Cracks (any) Reject Reject Reject Remove by grinding; verify by MT/PT; reweld per approved repair WPS
Undercut depth Max 1 mm; 0.25 mm at weld ends Max 0.25 mm Max 0.8 mm (UW-35) Grind and blend; do not weld fill without WPS coverage
Groove weld reinforcement (cap height) Max 3 mm Max 3 mm Max 3 mm (UW-35) Grind flush if exceeded; ensure no undercut is introduced
Overlap (cold lap) Reject Reject Reject Remove by grinding; reweld affected area
Porosity (surface) Max 6 mm cluster per 300 mm weld Not permitted Not permitted per UW-51 for RT-required welds Individual pores > 2 mm: reject and repair
Arc strikes Not permitted Not permitted Not permitted (UW-36) Grind flush; MT/PT; document on NCR
Weld profile (fillet — convexity) Max 0.07 leg length + 1.5 mm Flush preferred Per applicable code or drawing Grind if excessive; check throat is maintained after grinding
Fillet weld throat deficiency Max 2 mm, in ≤ 10% of weld length Max 2 mm in any 150 mm Per drawing minimum size Deposit additional weld metal per WPS
Common Weld Discontinuities — Location and Identification Undercut (weld toe groove) Overlap (cold lap at toe) Surface Porosity Crack (always reject) Lack of Fusion Root Concavity (underfill at root) cap height max 3 mm BASE METAL BASE METAL Defect locations shown schematically. All items shown (except undercut and reinforcement within limits) are rejectable under AWS D1.1 and ASME Section VIII.
Figure 3 — Cross-section of a completed groove weld showing the location of common weld discontinuities encountered during visual inspection. Cracks and overlap are always rejectable; undercut, reinforcement, and root concavity are evaluated against specific dimensional limits in the applicable code.

Why a Formal Welding Inspection Checklist Is Non-Negotiable

In regulated industries, the welding inspection checklist is not a discretionary quality improvement tool — it is a code-mandated requirement. ASME Section VIII Div. 1 Article UW-50 requires that all weld joints in pressure vessels be examined as specified by the applicable UW clauses. ISO 3834-2 Clause 12 requires documentation of all inspection activities. AWS D1.1 Clause 6 specifies the minimum inspection programme for structural steel welds. The ITP is the implementation document that maps these code requirements into the project’s specific inspection programme, with named hold points, responsible parties, and acceptance standards.

Beyond code compliance, a formal checklist delivers measurable operational benefits:

  • Defect prevention: Pre-weld and in-process checks catch conditions before they become defects embedded in completed welds — dramatically reducing NDT failure rates and rework costs.
  • Consistency: A checklist eliminates reliance on individual inspector memory. Every joint receives the same systematic examination regardless of shift, inspector, or project pressure.
  • Traceability: Signed inspection records create an audit trail that demonstrates due diligence to clients, regulatory bodies, and insurance underwriters.
  • Reduced rework: Industry data consistently shows that pre-weld fit-up inspection alone reduces NDT rejection rates by 30–50% on complex fabrication projects.
  • Legal protection: In the event of an in-service failure, comprehensive inspection records are the primary evidence that the manufacturer exercised reasonable care and followed the applicable code.
Practical Tip for CWIs: Develop a single-page site inspection card for each weld joint type on your project (e.g., process pipe butt weld, structural fillet weld, nozzle groove weld). The card should list the top 10 checks for that joint type in order of execution, with space for measured values and sign-off. Cards are faster to complete in the field than multi-page forms and dramatically reduce missed inspection steps. The full weld traveller is completed back in the QC office, referencing the field card entries. Test your ASME code knowledge with our ASME Section IX practice quiz.

Recommended Reference Books for Welding Inspectors

The following titles are the most widely used study and reference resources for practising CWIs, welding quality engineers, and inspection supervisors.

📘
Welding Inspection Technology — AWS CWI Study Guide
The official AWS publication for CWI exam preparation. Covers visual inspection, NDT methods, WPS/PQR review, code application, and weld acceptance criteria with worked examples.
View on Amazon
📗
Visual Inspection of Welds — A Practical Guide
Comprehensive guide to visual weld examination techniques, defect identification, measurement tools, and acceptance criteria under AWS, ASME, and ISO standards for working inspectors.
View on Amazon
📙
Nondestructive Testing Handbook — AWS / ASNT
Authoritative multi-volume reference on all NDT methods. Essential for inspectors who must select, specify, and review NDT procedures for welding quality programmes.
View on Amazon
📕
Quality Management in Welding — ISO 3834 Explained
Explains ISO 3834 quality requirements for fusion welding, including inspection planning, ITP preparation, welder qualification management, and documentation systems for fabricators.
View on Amazon

Disclosure: WeldFabWorld participates in the Amazon Associates programme (StoreID: neha0fe8-21). If you purchase through these links, we may earn a small commission at no extra cost to you. This helps support free technical content on this site.

Frequently Asked Questions

What documents must a welding inspector verify before welding starts?
Before any welding commences, the inspector must verify: the approved WPS is available at the work site and covers the specific joint, material, process, and position; the welder holds a current WPQ certificate covering the applicable variables; material test reports (MTRs) are available and match the heat numbers on the base material; filler metal certificates match the WPS classification; the ITP identifies all hold and witness points for this joint; and applicable drawings are at the correct revision level. Any missing document is a stop-work condition that must be resolved before the first arc is struck. For WPS preparation and qualification details, see our guide on how to prepare a WPS and PQR.
What are hold points and witness points in welding inspection?
A hold point is a stage in fabrication where work must stop completely and cannot proceed until the inspector has physically verified and signed off on that activity — no exceptions. Common hold points include joint fit-up verification, preheat confirmation before root pass, and NDT before PWHT. A witness point is a stage where the inspector should be present to observe the activity, but work may proceed after a defined waiting period (typically 24–48 hours) if the inspector does not attend and formally notifies the fabricator. Both types are defined in the Inspection and Test Plan (ITP) and are agreed upon by the manufacturer, client, and third-party inspector before fabrication commences.
What are the most common visual weld defects found during in-process inspection?
The most frequently encountered visual defects during in-process inspection are: undercut — a groove melted along the weld toe that reduces base metal cross-section (maximum 0.25 mm for cyclically loaded structures per AWS D1.1); overlap — weld metal that rolls over the toe without fusing, always rejectable; incomplete fusion — lack of bond between weld passes or between weld and base metal; arc strikes outside the weld zone — must be ground out and examined by MT or PT; excessive convexity or concavity in the weld profile; and spatter adhering to the base metal within the inspection zone. Each defect type has specific acceptance criteria in the applicable code that must be checked before signing off any pass.
How is interpass temperature monitored and what happens if it is exceeded?
Interpass temperature is measured using a calibrated contact thermometer, temperature-indicating crayon (Tempilstik), or infrared pyrometer at the weld toe, within 25–75 mm of the joint depending on the code. If the maximum interpass temperature specified in the WPS is exceeded, welding must stop immediately and the joint allowed to cool naturally before the next pass commences. On heat-sensitive materials such as P91 chrome-moly or duplex stainless steel, exceeding the interpass limit is a non-conformance requiring engineering disposition. In some project specifications, weld metal deposited above the interpass limit must be removed and rewelded. Never use forced water cooling on duplex stainless or chrome-moly steels.
Which NDT method is most appropriate for which weld defect type?
NDT method selection depends on defect type and material: Radiographic Testing (RT) is best for volumetric defects such as porosity and slag inclusions in butt welds but is less sensitive to tight planar cracks. Ultrasonic Testing (UT) and Phased Array UT are superior for planar defects such as cracks and lack of sidewall fusion — preferred for thick sections. Magnetic Particle Testing (MT) detects surface and near-surface cracks in ferromagnetic materials only. Liquid Penetrant Testing (PT) detects open surface cracks in any material including non-magnetic austenitic stainless steel. Visual Testing (VT) is mandatory for all welds regardless of other NDT requirements. Read our full overview of non-destructive testing methods for complete guidance.
What weld profile parameters are checked during visual inspection after welding?
Post-weld visual inspection examines: weld face appearance including uniform bead width, smooth ripple profile, and absence of pits or craters; weld toe geometry with smooth transition to base metal; throat thickness or leg length for fillet welds measured with a calibrated weld gauge; reinforcement height for groove welds (AWS D1.1 allows maximum 3 mm above base metal surface for statically loaded structures); undercut depth at the weld toe; surface porosity distribution; cracks — any crack in the weld or HAZ is always rejectable under all codes; and overlap or cold lap at the weld toes. All measurements must be made with calibrated instruments and recorded on the inspection report with the instrument reference number.
When is PWHT required, and how is it verified?
PWHT is required when specified by the construction code, engineering specification, or service conditions. Under ASME Section VIII Div. 1, PWHT is mandatory for P1 carbon steel welds above the thickness limits in UCS-56, for all P4 and P5 chrome-moly welds regardless of thickness, and for sour service applications per NACE MR0175. PWHT is verified by reviewing the time-temperature chart from calibrated thermocouples attached during heat treatment. The inspector checks: actual soak temperature within +/- 14°C of target; hold time at temperature from when the entire weldment reaches soak temperature; heating and cooling rates within specified limits; and adequate thermocouple coverage per code. The chart is retained as a permanent quality record and cannot be reproduced after the fact.
What records must a welding inspector maintain and for how long?
A welding inspector must maintain: weld maps identifying each joint with WPS number, welder ID, and date; pre-weld inspection reports covering fit-up, cleanliness, and preheat; in-process monitoring records for welding parameters and interpass temperatures; NDT reports for all examinations with examiner certification level and expiry; PWHT time-temperature charts and thermocouple calibration records; dimensional inspection records; any non-conformance reports and dispositions; and the final acceptance statement with the inspector’s signature and certification number. ASME Code stamped equipment records are typically retained for the life of the equipment or a minimum of 20 years. Always confirm the specific retention period with the applicable code, jurisdiction, and client contract requirements.

Further Reading on WeldFabWorld

Related Articles

Welding Inspection & Testing Ferrite Testing – Why It Matters in Stainless Steel Welding
ASME Codes & Standards Mechanical Testing in ASME Section IX – A Complete Guide
Welding Inspection & Testing What is Crack Tip Opening Displacement (CTOD)?
Welding Inspection & Testing Why Hot Cracking Occurs in Welds and How to Prevent It