PQR (Procedure Qualification Record) — What It Is, How to Fill It, and What Every Field Means
The Procedure Qualification Record is the documentary foundation of every qualified welding procedure in ASME-governed fabrication. Without a valid PQR, a Welding Procedure Specification cannot be certified; without a certified WPS, production welding on pressure-retaining components cannot legally begin. Yet despite its absolute centrality to fabrication compliance, the PQR is one of the most frequently incorrectly prepared, incompletely filled, and poorly understood documents in welding quality management.
In a typical ASME Section VIII pressure vessel fabrication contract, a welding quality audit will review the PQR package for every WPS used on the job. What auditors find — with surprising regularity — are PQRs with blank mechanical test fields, missing Charpy values for notch-toughness-required service, heat input not calculated, PWHT temperature ranges transcribed incorrectly from the WPS, and certifying signatures from individuals not authorised to certify on behalf of the manufacturer. Any of these deficiencies can result in the rejection of the entire procedure package and the requirement to re-qualify — halting fabrication, generating non-conformance reports, and triggering the schedule and cost consequences that follow.
This guide covers everything: the precise legal and technical relationship between the PQR and WPS, every field on the ASME QW-483 PQR form explained with the correct entry, all mechanical test requirements with acceptance criteria, the essential variable system and how it links PQR qualification to WPS range limits, and a comprehensive list of common PQR errors with their consequences and corrections. For the parallel WPS guide, see our complete WPS guide.
PQR vs WPS — The Fundamental Relationship QW-200
The relationship between the PQR and WPS is one of evidence and application: the PQR is the evidence; the WPS is the application of what the evidence demonstrates. Understanding this distinction is essential for correctly preparing and reviewing both documents.
The practical consequence of this relationship is direct: if an engineer wants to add a new position to an existing WPS, or extend the qualified thickness range, they must first check whether a supporting PQR already demonstrates that position or thickness. If not, a new qualification coupon must be welded, tested, and a new PQR prepared before the WPS can be revised. The PQR drives everything — the WPS cannot assert capabilities that no PQR has demonstrated.
Who Qualifies the Procedure and Who Certifies the PQR QW-103, QW-200.1
The manufacturer or contractor is responsible for qualifying the welding procedure and certifying the PQR. “Manufacturer” in ASME terminology means any organisation that constructs, repairs, or alters pressure equipment under an ASME stamp — it does not mean the raw material manufacturer. The certifying signature on the PQR must be from a person legally authorised to sign on behalf of the manufacturer organisation.
The Welder’s Role — Identified, Not Certifying
The welder who welded the qualification test coupon must be identified on the PQR by name and individual welder identification number (stamp number or ID code). However, the welder does not certify the PQR and does not own it. The PQR belongs to the manufacturer. The welder’s personal qualification is documented separately on a Welder Performance Qualification Record (WPQR or WPQ Test Record), which is a different document. A common error is confusing the welder’s qualification record with the procedure qualification record — they are entirely separate documents with separate content, format, and purpose.
The Authorised Inspector’s Role
The ASME Code Authorised Inspector (AI) does not certify the PQR, but has a specific role in the qualification process: the AI must have the opportunity to witness the welding and testing of the qualification test coupon. In practice, this means the AI must be notified in advance of the qualification test so they can witness it if they choose. If the AI does not attend, the manufacturer proceeds without them, but the qualification is still valid — the AI’s presence is an opportunity, not a requirement. Some Owner specifications are more stringent, requiring mandatory AI witnessing of qualification tests, but this is a contractual requirement beyond the ASME base code requirement.
The Qualification Process — Step by Step
-
Define the intended production weld scope
Before welding a single coupon, define precisely what production welds the PQR will need to support: the base material P-Number and Group, the welding process, the thickness range, the position, the filler metal F-Number, whether PWHT will be required, and whether notch toughness is required. This scope definition determines what type of coupon to weld and what tests to run — do it upfront or risk running unnecessary tests or missing required ones.
-
Prepare and review a pre-qualification WPS
Before welding the coupon, prepare a preliminary WPS that specifies the parameters you intend to use for the qualification weld. This is sometimes called the “test WPS” or “pre-qualification WPS.” It records the intended values for every variable — not production ranges, but specific target values for the qualification weld. The pre-qualification WPS is not certified but is used to ensure the coupon is welded in a controlled, documented manner.
-
Notify the Authorised Inspector
Notify the AI of the planned qualification test date and location with adequate advance notice. The AI may or may not attend — that is their decision — but their opportunity to witness must be documented. Proceed with the test regardless of AI attendance, unless the project contract specifically requires AI witnessing.
-
Weld the test coupon — recording actual parameters
Weld the test coupon under controlled shop conditions. During welding, measure and record actual parameter values — not the nominal values from the pre-qualification WPS, but the actual measured values for each pass: amperage from a calibrated ammeter, arc voltage from a voltmeter at the electrode, travel speed measured with a stopwatch and measured distance, interpass temperature measured with a calibrated contact thermometer. These actual values are what go on the PQR — they are the record of what was done. Never copy nominal values from the WPS onto the PQR fields that require actual measured values.
-
Submit coupon for mechanical testing
After welding (and after PWHT if PWHT is required by the test), submit the coupon to an approved mechanical testing laboratory. Specify the test types required per ASME Section IX for the applicable weld type: tensile, bend (face/root/side), and Charpy impact if notch toughness is required. Ensure the laboratory provides certified test reports stating actual test results, specimen dimensions, and a pass/fail conclusion against the applicable code requirements.
-
Complete the PQR form and certify
Fill out the PQR form (QW-483 for groove welds, QW-484 for fillet welds, QW-485 for stud welds) with all required information. Transfer the actual welding parameters from the weld data records, transfer the test results from the laboratory reports, and complete all identification, base material, filler metal, and technique fields. Have the completed PQR reviewed by a qualified welding engineer or Level III, then obtain the authorised manufacturer certification signature and date.
-
Write the supporting WPS using the qualified PQR
With the certified PQR in hand, write the production WPS by applying the Section IX essential variable rules to determine the qualified ranges for each parameter. Reference the PQR number(s) on the WPS. Certify the WPS. The document package — PQR + WPS — is now complete and ready for Authorised Inspector review and project submission.
Test Coupon Requirements QW-200.4, QW-461
The test coupon is the physical demonstration that the welding procedure works. Its dimensions, joint geometry, position, and material must be correct — an incorrectly configured coupon will produce a PQR that does not cover the intended production welds, requiring the test to be repeated.
| Parameter | Requirement | Notes |
|---|---|---|
| Coupon material specification | Same P-Number and Group Number as production base material | Must be from a specification within the same P-Number/Group — e.g. A106 Gr.B (P-No.1 Gr.1) qualifies for other P-No.1 Gr.1 materials. Mill cert required for coupon base material. |
| Coupon thickness (groove weld) | Minimum 19 mm (3/4 in) recommended for full test range; thinner allowed with reduced qualified range | Coupon thickness determines qualified production thickness range: if coupon t ≥ 19mm, qualifies from 1.5 mm to 2t. If coupon t <19 mm, qualified range is more limited. |
| Joint type | Groove butt weld for groove weld WPS; fillet weld coupon for fillet weld WPS | Groove weld PQR qualifies groove welds AND fillet welds. Fillet weld PQR qualifies fillet welds only. |
| Minimum coupon dimensions | 150 mm (6 in) wide × 300 mm (12 in) long minimum (each plate) | Longer coupons allow more test specimens to be cut. End portions (first 50 mm each end) are typically discarded — ensure sufficient qualified length remains for all required specimens. |
| Welding position | Position used during coupon welding determines positions qualified | 2G position qualifies 1G and 2G. 3G qualifies 1G, 2G, 3G, 4G. 6G qualifies all positions. See QW-461.9 for full position qualification matrix. |
| PWHT on coupon | If production welds require PWHT, coupon must be PWHT using the same temperature range and hold time as specified in the WPS | PWHT conditions are essential variables — a change in PWHT temperature range requires a new PQR. Coupon PWHT must be performed before mechanical testing, not after. |
How to Fill the PQR — Section by Section
The ASME QW-483 PQR form is the standard format for groove weld procedure qualification records. The following walkthrough covers every section of the form with the correct entry for each field, the common error for each, and a note on why it matters. The interactive form mock-up below shows how a correctly completed PQR header section appears.
Section 1 — Record Identification and Header
Section 2 — Base Materials
The P-Number System — Why It Is Critical
The P-Number (and Group Number for impact-tested materials) is the single most important base material identifier on the PQR because it determines the range of production materials the PQR qualifies. A PQR on P-No. 1 Group 1 (carbon steel) qualifies welding on all P-No. 1 Group 1 materials, regardless of whether the specific production material specification differs from the coupon specification. A change in P-Number is an essential variable requiring a new PQR.
For a complete guide to P-Numbers, Group Numbers, and F-Numbers including all common material assignments, see our detailed P-Number, F-Number, and A-Number reference guide.
Section 3 — Filler Metals
F-Number and A-Number — Why Both Are Recorded
The F-Number and A-Number serve different purposes in the PQR qualification framework. The F-Number (filler metal group per QW-432) governs the usability characteristics of the electrode — whether it has comparable welding characteristics (e.g. all low-hydrogen SMAW electrodes are F-No. 4; all cellulosic SMAW are F-No. 3). A change in F-Number is an essential variable because it changes the welding behaviour and, for some process-position combinations, the achievable weld quality.
The A-Number (weld metal composition group per QW-442) governs the chemical composition of the deposited weld metal — A-No. 1 is carbon steel weld metal, A-No. 8 is austenitic stainless weld metal. A change in A-Number is an essential variable because it changes the metallurgical composition and properties of the weld metal itself, directly affecting the mechanical test results the PQR is demonstrating.
Section 4 — Welding Conditions (Actual Parameters)
Section 5 — Technique
Mechanical Test Results — Overview
The mechanical test section of the PQR is where the qualification is actually demonstrated — where the coupon proves it meets the required mechanical properties. This section records the actual test results from the laboratory, and the acceptance criteria against which each result is evaluated. A PQR with passing mechanical test results is a qualified procedure; one with failing results is a failed qualification that must be repeated.
GROOVE WELD (butt weld) — QW-451:
Tensile test: 2 specimens (QW-150) — reduced section or full section
Bend tests: Face bend ×2 + root bend ×2 [for t < 19 mm, OR
Side bend ×4 [for t ≥ 19 mm]
Impact (Charpy): Required when supplementary essential variable QW-250 applies
3 specimens from weld + 3 from HAZ minimum
FILLET WELD (QW-180):
No tensile or bend tests required
Macro examination of fillet cross-section — fusion, crack detection
Fracture test (break test) on one specimen
Heat Input Calculation (record on PQR):
HI (kJ/mm) = [V (volts) × I (amps) × 60] / [1000 × Travel Speed (mm/min)]
Maximum heat input is a supplementary essential variable when impact testing is required.
Tensile Tests QW-150, QW-153
Two transverse tensile specimens are required for groove weld PQR qualification. Each specimen is machined from the coupon, with the weld axis perpendicular to the load direction, and pulled to failure in a calibrated testing machine.
Tensile Test Acceptance Criteria QW-153
The tensile specimen must not break in the weld at a stress below the specified minimum tensile strength of the base metal (or the lower of the two base metals for dissimilar joints). If failure occurs in the base metal or HAZ at a stress below the specified minimum tensile strength of the base metal, the test is acceptable only if the failure occurred at a stress of not less than 95% of the specified minimum tensile strength of the base metal. Failure in the weld metal at a stress below the base metal minimum is a failure — the procedure qualification has not been demonstrated and must be repeated.
Bend Tests QW-160, QW-163
Bend tests are the primary ductility verification in PQR qualification. For material less than 19 mm thick, two face bend and two root bend specimens are required. For material 19 mm thick or greater, four side bend specimens are used instead — side bends more accurately represent the through-thickness ductility of thick-section welds and detect laminar defects that face or root bends might miss.
| Specimen Type | When Used | What It Tests | Bend Mandrel Diameter | Acceptance Criterion |
|---|---|---|---|---|
| Face Bend | t < 19 mm | Ductility of weld metal at the crown surface — detects crown porosity and cracking | 4t for most P-No. 1–6 materials | No open discontinuity >3 mm in any direction; no corner cracks >6 mm (except from slag inclusions) |
| Root Bend | t < 19 mm | Ductility of weld root and root HAZ — the most crack-sensitive zone; detects incomplete fusion and root cracks | 4t for most P-No. 1–6 materials | Same as face bend — no open discontinuity >3 mm |
| Side Bend | t ≥ 19 mm (or any t for dissimilar metals) | Full through-thickness ductility — tests the entire cross-section of the weld and HAZ in a single specimen | 4t for most materials (based on specimen thickness, nominally 10 mm) | No open discontinuity >3 mm in any direction after bending through minimum 180° (or to the specified angle for the material) |
Charpy Impact Tests (Notch Toughness) QW-170, QW-171, QW-172
Charpy V-notch impact tests are required as supplementary essential variables when the production WPS is being written for an application that requires demonstrated notch toughness — notably low-temperature service, thick-section pressure vessels under ASME Section VIII UG-84, and nuclear applications. When impact tests are required, they become supplementary essential variables, meaning changes to the welding conditions that affect toughness (heat input increase, preheat decrease, PWHT change) require re-qualification of the impact test.
| Specimen Location | Number Required | Notch Position | Test Temperature | Acceptance (Typical) |
|---|---|---|---|---|
| Weld metal centre | 3 specimens minimum | Notch at weld centreline | Per design requirement (e.g. −20°C, −46°C) | Average ≥27 J; no individual <20 J (ASME UG-84 general requirement) |
| HAZ (heat-affected zone) | 3 specimens minimum | Notch at fusion line or 2 mm from fusion line — per procedure | Same as weld metal specimens | Average ≥27 J; no individual <20 J (unless Owner spec is more stringent) |
| Additional locations | As specified by Owner or code | May require notch at FL, FL+2mm, FL+5mm | Same | Per Owner specification |
Hardness Tests QW-200, Owner/NACE requirements
Hardness testing is not mandated by ASME Section IX as a standard PQR test requirement for all applications, but it is required by NACE MR0175/ISO 15156 for sour service applications (to demonstrate HAZ hardness does not exceed HRC 22), by ASME Section VIII for some P-No. 5B (P91) applications, and by most Owner company specifications for critical service. Where hardness testing is required, the results must be recorded on the PQR and the specimen location (weld metal centre, HAZ, and base metal at standardised positions per the applicable hardness traverse pattern) documented clearly.
| Location | Measured Hardness | Maximum Allowed (Sour Service) | Result |
|---|---|---|---|
| Weld metal (centre) | 178 HV10 | 248 HV10 (HRC 22) | PASS |
| HAZ (coarse-grained, 1 mm from fusion line) | 231 HV10 | 248 HV10 (HRC 22) | PASS |
| HAZ (fine-grained, 3 mm from fusion line) | 195 HV10 | 248 HV10 (HRC 22) | PASS |
| Base metal (beyond HAZ) | 162 HV10 | Reference only | Reference |
Essential Variables — How They Link PQR to WPS Range Limits
Essential variables are the welding conditions and parameters whose change from the qualified range requires a new PQR. They are the mechanism by which ASME Section IX ensures that the WPS always falls within the demonstrated capabilities of its supporting PQR(s). Understanding which variables are essential — and which are not — is fundamental to correctly writing WPS range limits from a PQR.
| Variable | Type | Qualified Range from PQR | Section IX Reference |
|---|---|---|---|
| Change in welding process | Essential | Same process as qualified only; each process requires its own PQR | QW-250 (all processes) |
| Change in base material P-Number | Essential | Specific P-Number combinations qualified; joining two P-No. 1 base metals qualifies P-No. 1 to P-No. 1 only | QW-253/QW-403 |
| Change in base material Group Number (when impact tested) | Supplementary Essential | Specific Group Number qualified; P-No. 1 Gr. 1 does not qualify P-No. 1 Gr. 2 when impacts required | QW-403.6 |
| Change in F-Number of filler metal | Essential | Same F-Number only; F-4 qualification does not qualify F-3 | QW-404.4/QW-432 |
| Change in A-Number of deposited weld metal | Essential | Same A-Number only; A-1 (CS) does not qualify A-8 (austenitic SS) | QW-404.5/QW-442 |
| Increase in heat input (supplementary, impact) | Supplementary Essential | Maximum heat input on WPS cannot exceed qualified maximum (QW-409.1) | QW-409.1 |
| Change in PWHT (temperature range) | Essential | WPS PWHT temperature range must fall within PQR qualified range | QW-407.1 |
| Addition or deletion of PWHT | Essential | PQR with PWHT qualifies only procedures that include PWHT; without PWHT qualifies without only | QW-407.1 |
| Change in current type or polarity (DCEP to DCEN or AC) | Essential | Same polarity as qualified | QW-409.2 |
| Addition of backing (or change from with to without backing) | Essential | PQR qualified without backing qualifies procedures with or without backing; PQR with backing qualifies with backing only | QW-402.1 |
| Decrease in minimum preheat (supplementary, impact) | Supplementary Essential | Minimum preheat on WPS cannot be less than qualified in PQR when impacts required | QW-406.3 |
| Increase in maximum interpass temperature (supplementary) | Supplementary Essential | Maximum interpass on WPS cannot exceed PQR qualified maximum when impacts required | QW-406.3 |
| Joint design (groove angle, root gap) | Non-Essential | Not restricted by PQR — can be changed on WPS without re-qualification | QW-402 |
| Electrode size (diameter) | Non-Essential | Not restricted by PQR — any electrode size within F-Number is acceptable | QW-404 |
| String vs weave bead | Non-Essential | Not restricted — either technique acceptable on WPS regardless of PQR technique | QW-410 |
From PQR to Supporting WPS — Deriving the Qualified Ranges
Once the PQR is certified, the WPS is written by applying the Section IX rules to the actual PQR values to determine the allowable ranges for production welding. This is how each key parameter translates:
BASE MATERIAL THICKNESS (QW-451):
PQR coupon thickness t = 25.4 mm
WPS qualified range: 1.5 mm (minimum) to 51 mm (= 2t) maximum
DEPOSITED WELD METAL THICKNESS (QW-451):
PQR deposited weld metal thickness (all passes) = let’s say 22 mm
WPS qualified range: up to 2 × 22 mm = 44 mm maximum deposited
HEAT INPUT (when supplementary essential — impacts required):
PQR maximum heat input = 1.44 kJ/mm (measured)
WPS maximum heat input = 1.44 kJ/mm (cannot exceed PQR maximum)
WPS minimum heat input = typically 0.75 × PQR minimum (some Owner specs)
PREHEAT (supplementary essential when impacts required):
PQR minimum preheat = 75°C
WPS minimum preheat = 75°C (cannot be less than PQR minimum when impacts required)
PWHT:
PQR PWHT range = 595°C to 635°C
WPS PWHT range = 595°C to 635°C (must fall within PQR qualified range)
The WPS can specify tighter ranges than the PQR — never wider ones.
Common Errors in PQR Documentation — and Their Consequences
| Error | Consequence | Correct Practice |
|---|---|---|
| Recording nominal WPS values in the “actual” fields instead of measured values | PQR does not represent what was actually done — heat input calculation is wrong, qualified ranges may be incorrect. Potential falsification of a quality record. | Measure amps, volts, and travel speed with calibrated instruments during coupon welding. Record only measured values on the PQR. |
| Blank fields — especially mechanical test results, PWHT records, heat input | PQR is incomplete and will be rejected by Authorised Inspector review. Cannot certify an incomplete document. | Complete every field. Where a test is not required (e.g. no Charpy required), write “N/A — not required” rather than leaving blank. |
| No reference to the supporting PQR number on the WPS | WPS is not traceable to its qualification basis — AI cannot verify the qualification without this link. | Every WPS must reference the PQR number(s) that support it in a designated field. Multiple PQRs may support one WPS if the combination is documented. |
| WPS ranges exceed PQR qualified limits (e.g. WPS max thickness > 2t from PQR) | The WPS claims a capability the PQR has not demonstrated. Invalid qualification — production welds made under the over-ranged WPS are unqualified. | Apply Section IX range rules rigorously when deriving WPS limits from PQR actual values. Have a qualified welding engineer review the WPS-to-PQR mapping. |
| PWHT performed on the PQR coupon after mechanical testing instead of before | Mechanical test results do not represent the post-PWHT material condition that production welds will have. PQR does not qualify PWHT’d production welds. | PWHT must be applied to the test coupon BEFORE mechanical testing. Document PWHT with time-temperature chart attached to the PQR. |
| Using incorrect mandrel diameter for bend tests (especially for stainless steel or high-alloy materials) | Bend test specimens may crack at a mandrel size that would pass for carbon steel but is too small for the lower ductility alloy — or vice versa, the test is easier than required. | Check QW-163 for the correct guided bend test jig dimensions for the specific P-Number being qualified. Carbon steel (P-No. 1) uses 4t mandrel; some alloys require different values. |
| Omitting Charpy impact tests when required by the design service temperature or Owner specification | PQR does not demonstrate notch toughness. WPS written from it cannot be used for impact-required service without supplementary qualification. | Always check whether the intended service requires Charpy qualification before setting up the test coupon. Re-qualification with impacts requires a new coupon. |
| PQR certified by a person without authority to sign on behalf of the manufacturer | PQR certification is legally invalid — not an authorised record of the manufacturer’s qualification. | Confirm the certifying signatory is named in the manufacturer’s QA manual as authorised to certify PQRs on behalf of the organisation. |
| Altering a certified PQR after certification (correcting errors by crossing out and overwriting) | A PQR is a permanent historical record. Post-certification changes that are not formally documented void the integrity of the record. Changes must be reissued through a formal revision process. | If errors are found after certification, issue a superseded revision with a revision history block. Retain the original. Never overwrite a certified PQR without formal change control. |
Recommended References
Disclosure: WeldFabWorld participates in the Amazon Associates programme (StoreID: neha0fe8-21). If you purchase through these links, we may earn a small commission at no extra cost to you. This helps support free technical content on this site.